St Josephs Convent Haslemere, Surrey

St Josephs Convent Images

Project Brief

The refurbishment of a disused hospital building into accommodation for the resident sisters.

Project Team

Architect: Frederick Gibberd Partnership

Engineer: Scott Wilson Group

Project Description

The project comprised the re-roofing and complete strip out of the building. Additional insulation was applied to the external walls, new en-suite facilities to each bedroom were created along with a new dining room, commercial kitchen and communal area.

The external render was repaired and the building completely redecorated.

The project was completed on time and within the clients budget.

St Josephs Convent Images

Client
Holy Cross Hospital

Contract Value
£1.4 million

Duration
40 weeks

Sector
Residential

Procurement Route
Negotiated

Form of Contract
JCT 2009 Design and Build

Completed
January 2011