Project Brief

Stereopsis employed W. Stirland to carry out the conversion of a disused church into a new Ophthalmic Centre in Worthing City Centre. All works were carried out to ensure the building’s original character was retained.

 

Project Team

Architect: Martin Critchell Architects

Engineer: Hemsley Orrell Partnership

CDM Coordinator: Grant Associates (Chichester)

 

Project Description

The works comprised of the clearing and stripping out  the site including the demolition of the existing portacabin followed by the extension, alteration, refurbishment and repair works to the existing building including the installation of additional floors to form the new Ophthalmic Centre and associated operating theatres.

 

Worthing Ophthalmic Centre Images

Client
Stereopsis

Contract Value
£2.5 million

Duration
41 weeks

Sector
Health

Procurement Route
Traditional Tender

Form of Contract
JCT 2011 Building Contract without Qunatities

Completed
July 2013